Progress in Construction
UPTO March 2016 - Piling Work Completed
April 2016 - Mud Digging & De-watering
April 2016 - Breaking of Piles & Leveling
May 2016 - Termite Treatment Going on
May 2016 - PCC Work Under Process
June & July 2016 - Raft of one block completed
August 2016 - Casting of Retaining Wall & Column of Block B
September 2016 - Casting of Basement of Block B
October 2016 - Casting of Stilt Floor Slab of Block B
November 2016 - Casting of First Floor Slab of Block B
December 2016 - Casting of Second Floor Slab of Block B and PCC Work of Block C
January 2017 - Casting of Third Floor Slab of Block B
February 2017 - Casting of Fourth Floor Slab of Block B
March 2017 - Casting of Fifth Floor Slab of Block B and Steel Work of Raft of Block C
APRIL 2017- Shuttering of 6th floor slab of Block B and Completion of steelwork of raft of Block C
May 2017 - Casting of Raft Block C
June 2017 - Casting of 6th Floor Slab of Block B
July 2017- Slab of basement of block C
August 2017- Casting of Ground floor slab of Block C
September 2017- Completion of Sample flat.
October 2017- Casting of 7th floor slab of block B & 1st floor of Block C
November 2017- Casting of 8th floor slab of block B
December 2017- Casting of 2nd floor slab of block C
January 2018- Casting of 3rd floor slab of Block C
February 2018- Commencement of raft of Block A
March 2018 - Casting of 4th floor slab of Block C
April 2018- Termite treatment & Base preperation of Block D
May 2018- Casting of raft of Block A
June 2018- Casting of 5th floor slab of Block C
27 December 2018- Casting of Basement Slab of Block A
31st December- New RMC and Concrete pump installed at the site
1 -feb-2019 Casting of stilt floor in block A
March 2019 - Casting of 1st Floor Slab of Block A
April 2019 - Casting of 2nd Floor Slab of Block A
May 2019- Casting of 3rd Floor Slab of Block A
June 2019- Casting of Block D Raft
June 2019- Casting of 4th Floor Slab of Block A
July 2019- Casting of raft of the Podium
August 2019-Casting of 5th floor slab of Block A
August 2019- Casting of basement slab of Block D
September 2019- Casting of 6th floor slab of Block A
October 2019- Casting Of 1st Floor Slab of Block D
November 2019- Casting of 7th Floor Slab in Block- C
November 2019- Casting of 8th Floor Slab of Block A
December 2019- Casting of 2nd Floor Slab of Block D
December 2019- Casting of 8th Floor Slab in Block C
January 2020- Casting of 9th Floor Slab in Block A
January 2020- Casting of 9th Floor Slab In Block C
January 2020- Casting of 3rd Floor Slab in Block D
February 2020- Casting of 10th floor slab of Block C
February 2020- Casting of 4th floor slab of Block D
March 2020- Casting of 10th floor slab in Block A
May 2020- Casting of 9th Floor Slab of Block B
June 2020- Casting of 11th Floor Slab of Block A
June 2020- Casting of 5th Floor Slab of Block D
July 2020- Casting of 10th Floor Slab of Block B
July 2020- Casting of 6th Floor Slab in Block D
July 2020- Casting of 12th Floor Slab in Block A
August 2020- Casting of 7th Floor Slab of Block D
August 2020- Casting of 11th Floor Slab of Block B
September 2020- Casting of 12th Floor Slab of Block B
October 2020- Casting of 8th Floor Slab of Block D
November 2020- Brickwork in Block A
December 2020- Brick Work of 6th Floor in Block D
January 2021- Block B Brick work done till 11th Floor
February 2021 Brick work completed in Block B
February 2021 Tile work in Block D
March 2021- Shuttering work till 9th floor in Block D
March 2021 Tile work completed till 6th floor in Block A
March 2021 Casting of 10th floor slab of Block D
March 2021 Gypsum work in block B till 9th floor
April 2021- Tile work in second floor of Block D
May 2021- Carpenter work in 7th floor of Block B
June 2021- Brick work till 7th floor of Block D
July 2021- Internal Plaster work in Block B
August & September 2021- Plastering, Putty and Primer in front elevation of Block B
October 2021- Plastering, Putty & Primer in right side small elevation of Block-B
November & December 2021- Plastering, Putty & Primer in left large side elevation of Block-B